System 800xA with batch processing and ERP integration for Chr. Hansen

The factory’s control systems, user interfaces, process integration and reporting systems have been supplied by ABB Danmark in close cooperation with Chr. Hansen’s own engineering group.

Share this page

Chr. Hansen’s latest factory in Avedøre is intended to secure the company’s continuing leading position in the market for advanced food cultures for the dairy industry.

Optimal automation solution for demanding food culture production

The Danish company, Chr. Hansen A/S, is one of the world’s largest producers of natural food ingredients such as cultures, enzymes, colours and functional ingredients. The company’s most important products include cultures for the production of fermented milk and cheese products. Chr. Hansen has research and development centres in more than 20 countries all over the world and factories in Denmark, China, France and the USA, among others.

To keep pace with the increasing demand on the world market for advanced food cultures, Chr. Hansen needed to build a new factory for the production of food cultures in Avedøre. There were only 15 months from the decision to proceed until the finished factory had to be ready for production – a very short time horizon for such a complicated and complex project.

”The new culture factory, which represents an investment of 50 million euro, is intended, in addition to supplying the European market with feed cultures, to be a reference project for any future factories that we may establish around the world,” says Thomas Düring, Director of Chr. Hansen. Thomas Düring is responsible for the company’s 24-man strong engineering group, which maintained close cooperation with ABB in Denmark over the entire course of the project.

Main facts

Industry Food and beverage manufacturing
Customer Chr. Hansen
Country Denmark
Solutions
  • Complete process control system for batch processing, 800xA Batch Management
  • ERP system
  • MES system
  • Production reporting
ABB supply
The production control system, which is based on ABB’s proven System 800xA, receives close on 5,500 signals, of which around 300 relate to feedback about the state of production and specific information of a critical nature with regard to traceability and consequently food safety.

Efficient and flexible project execution

A crucial consideration for Chr. Hansen was that the company’s own engineering group could be included in the project team that would be responsible for the planning and implementation of the extensive project. Not only for the sake of dynamic project management, but also to ensure that the business would have access to the necessary skills to enable it to undertake programming and maintenance of the application code for the control system.

At the time when ABB became involved, only about seven months remained until the project had to be completed and the factory had to be ready for production. This made it necessary to establish a particularly efficient and flexible project organization, which was in a position to take whatever steps were necessary at short notice in order to deal with peak loads and bottlenecks in the project. Chr. Hansen wrote its own design specifications based on the concept that they had drawn up jointly with ABB. That is why it was also natural for the company to assign 5-6 men to the project team, which, furthermore, was made up of Danish and foreign employees of ABB. 
“The production of feed cultures is Chr. Hansen’s largest business area. That is why it was so important to ensure that neither bureaucratic obstacles nor a defective infrastructure could have a disturbing effect and disrupt the extremely strict timetable for the implementation of the project,” says Thomas Düring.

Engineering and integration with 800xA

“When ABB entered the project, the I/Os were already in place. Our task was thus to bind the units together and to undertake part of the actual engineering and integration, both forwards towards the process and backwards towards Chr. Hansen’s ERP system,” relates Per Larsen, Technology Manager with ABB. And I believe that I am speaking on behalf of everyone when I state that the successful implementation of the project can be attributed to a high degree, in addition to ABB’s firstclass hardware and software products, to the fact that we were able to manage the project extremely efficiently in spite of the time constraints and the many changing resources.

Thomas Düring, Director, Chr. Hansen
“On the engineering side, ABB was an outstanding partner. They were very flexible and capable of putting the necessary resources into the task at very short notice. We built the factory in only 15 months, so we were working under full pressure from the start.”

Batch process with customized MES system

ABB has supplied the overriding process control system for batch processing, which is structured on the basis of ABB’s standard libraries, but with the necessary client-specific adaptations. 

“The system is based on the S88 concept, and the applications are based on ABB’s standard libraries for batches, and components, that are designed to satisfy the requirements of S88,” explains Project Manager Jim Nielsen from ABB. The components are built up with the help of objects, which gives a high degree of reuse. The system is based on interactive process images designed specifically for the plant. This means that, with a few clicks on the individual element, it is possible to see all the values, obtain an overview and details and an overview of sources of error. 

“The very fact that we had access to these already tested and validated libraries contributed to our ability to ensure that we could live up to Chr. Hansen’s strict timetable. At the same time, the modular nature of the design offers a unique opportunity to extend and modify the system, little by little as the need arises,” says Jim Nielsen.

The batch control system is prepared for the reuse and development of recipes without further adaptation. It is also possible to place the production orders in a queue, so that they can be processed in turn as the production equipment becomes free. The system itself is also able to work out which recipes must be processed and the sequence in which this must take place to ensure appropriate utilization of the production plant. This means that a number of batches at a time can be started, which can subsequently be processed in parallel. 
The system is based on interactive process images designed specifically for the plant. This means that, with a few clicks on the individual element, it is possible to see all the values, obtain an overview and details and an overview of sources of error.

Communication with the ERP system

Apart from the many specific requirements for the process control system, a further requirement was that ABB’s system should be able to communicate upwards to CEOPS, Chr. Hansen’s own overriding ERP system developed in-house. In order to be able to guarantee this, ABB developed a client-adapted interface, which ensures that production plans can be transferred from the ERP system to the MES system, and that all the relevant data from production can be sent to the ERP system.

The production control system, which is based on System 800xA, receives close on 5,500 signals, of which around 300 relate to feedback about the state of production and specific information of a critical nature with regard to traceability and consequently food safety. All the data are collected in a database (Microsoft SQL server), from where reports can be generated, so that it is possible to see all process and product parameters, including which raw materials have been used, their origin and preparation. 

Project insights

Software

Complete process control system for batch processing based on the S88 standard. Uses ABB’s standard libraries for batches. ABB’s batch system has given Chr. Hansen the following advantages:
• Developed recipes can be reused and developed without the need for additional engineering.
• There is the possibility to place several batches in a queue.
• The batch system processes several batches in parallel. The system itself works out what recipes must be processed on what equipment depending on the operating status.
• The system is prepared for preventive maintenance. This means that all the process and IT components can be monitored so that breakdowns can be minimized.

ERP integration

The production system is integrated with Chr. Hansen’s business system. This allows the production plans from the business system to be transferred automatically to the production system. The operators can then see the planned production in the form of a GANTT chart and can start and monitor production from here on a continuous basis. A combined overview of the entire production process in the individual production orders is obtained in this way. When a production order is complete, production data are transferred from the production system to the business system.

Production reporting

All production data are collected in a database (Microsoft SQL Server), and batch reports can be generated from this. Reports can be defined, displayed, printed or saved for subsequent documentation. Reports can be displayed on all the PCs connected to the production system without the installation of additional software. Reports can thus also be displayed on office PCs.