Conveyor CV-02 is 20MW and the second of TAKRAF’s mega 11,000 tph gearless drive conveyors which will convey crushed copper ore from the underground mining area to the surface - a distance of 13km.
It is fed by conveyor CV-01, also 20MW and a similar length, with both conveyors overcoming significant elevation change of more than 1,000m as they transport ore from the first level of the underground mine system to the surface.
Conveyor CV-02 feeds into another TAKRAF conveyor, this time an overland conveyor of 15MW, also using advanced gearless drive technology.