For Aasta Hansteen FPSO, ABB Process Performance reviewed key systems and found 57 operability issues ahead of the process start-up. All issues was fixed by re-engineering the process control logic.
Estimated customer value
40 days reduced downtime
2700 man-hours saved during commissioning
Less stress on equipment
Less quick-fixes done offshore